Town of Union Country Club Road over Patterson Creek Bridge Rehabilitation

OwnerTown of Union, NY
Completion Date2019
Construction Cost$1,330,000
ServicesPreliminary & Final Bridge & Highway Design, Design Report Preparation, Environmental Documentation, Public Participation, Utility Coordination, Design Survey & Mapping, Bid and Construction Support, Construction Inspection
Project Description

This $1.33 million project involved the rehabilitation of the existing 47.5-foot, single span, steel beam Country Club Road over Patterson Creek Bridge in Broome County, NY and the reconstruction of approximately 400 feet of the bridge approach roadways.

Read More

The project includes superstructure replacement with new galvanized steel beams with precast deck panels, sidewalks and Texas Bridge Barrier, substructure repairs, bearing replacement, heavy stone fill scour protection and a temporary on-site pedestrian bridge. Due to high traffic volumes, bridge closure was limited to three weeks by utilizing Accelerated Bridge Construction (ABC) technology precast deck panels. This was a locally managed, federally-funded, “Bridge NY” project, which mandated use of New York State Department of Transportation design procedures and criteria and an adherence to an 18-month consultant design schedule.