Iowa Department of Transportation City of Dubuque Box Culvert

Iowa Department of Transportation City of Dubuque Box Culvert

OwnerIowa DOT
Completion Date2018
ServicesStructural Design
Project Description

The City of Dubuque received funding for improvements to storm sewers to prevent the ongoing flooding that has plagued the area.

Read More

The overall project included the reconstruction of the street and relocation of all underground utilities. Installation of a large box culvert in the middle of residential streets proved challenging because of the utility relocation and high traffic area. Future projects will extend this large storm sewer to prevent residential flooding in other surrounding areas. The estimated completion date of the entire project is 2021. In addition to design computations and drawings, Delta Precast provided a reinforcing summary for over 1,000 feet of 10’ x 5’ box culverts.